top of page

ACHIEVEMENTS

Successful

Recovered in excess of £5m of previously disputed Compensation Events, on behalf of BAM Nuttall Ltd, on their £100m infrastructure refurbishment scheme.

SUCCESSFUL

Negotiated agreement on multiple disputed final accounts, and projects close to completion, whereby Turner & Townsend (construction cost consultants) were appointed by the employer to scrutinise defined costs on numerous Civil Engineering / Water Industry Spillway projects.

Successful

Represented Telent Technology Services in the capacity of Commercial Manager, protecting their commercial interests in relation to a £3m delay & disruption claim on a Network Rail SCADA Upgrade Project.

successful

Defended Smith Brothers Contracting Ltd, against numerous spurious claims made by their subcontractor, with cumulative reductions agreed in the region of £500,000.

successful

Recovered circa £400,000 in previously disputed Compensation Events, on behalf of Tillhill Forestry, who had been appointed as a specialist subcontractor by Balfour Beatty Civil Engineering on the A46 Highways Improvement Scheme.

bottom of page